BMS — building management system
scope outline.

BACnet / Modbus building bus integrating HVAC, lighting, energy, fire-alarm status, generator and UPS into a single supervisory dashboard. Operator-facing.

In scope

Point-list design across HVAC, lighting, energy, fire interface • Schedule design — occupancy, set-point, holiday calendars • Trend and alarm-routing config • Dashboard design per operator role • Energy submetering integration

Out of scope

HVAC equipment supply and ducting • Field instrumentation supply where not part of the BMS package • Energy audit and ECBC compliance certification

· Documents required

Materials the consultant needs before specification starts.

  • HVAC scheme and equipment schedule

  • Lighting circuit and DALI / KNX gateway list

  • Energy metering scope

  • Operator team profile and shift schedule

· Site survey

Pre-design walk-through verifications.

  • Existing BMS scope if retrofit — point list, vendor licence position

  • Riser space for BMS controller cabinets

  • Network availability at each controller location

· Deployment checklist

Engineering items every install of this discipline carries.

  • BACnet-IP backbone with Modbus / proprietary islands at the field layer

  • Schedule per operating zone with holiday override

  • Alarm-routing with escalation rules per role

  • Trend logging for every energy meter at 15-min intervals minimum

  • Operator dashboard role-based access

· Coordination with other trades

Works owed to / from other disciplines.

  • Fire: read-only fire-alarm zone status into the BMS supervisory layer

  • Networking: VLAN segregation; controller-server on dedicated rail

  • UPS: status from UPS / generator into BMS for operator awareness

  • Lighting: DALI / KNX gateway integration

· Commissioning

Measurable artefacts produced at handover.

  • Schedule test against a holiday-week scenario

  • Alarm-routing test per alarm class

  • Energy meter calibration against external reference

  • Dashboard role test per operator profile

  • Database snapshot baseline

· Handover

What the building team takes ownership of.

  • Point-list and schedule documentation

  • Dashboard layout files

  • License keys and renewal schedule

  • Operator training certificate

· Risk register starter

Risks worth tracking from day zero.

  • Vendor major-version upgrade requiring full license renegotiation

  • Field sensor drift silently degrading control loops

  • Schedule misfires after holiday-list updates

· Exclusions and assumptions

What is not in scope; what we assume to be true.

  • Excludes HVAC equipment and field instrumentation supply

  • Assumes building has a stable network backbone